Management spoke to investors on Thursday morning following release of the company's fourth-quarter and full-year 2022 results.

Updated May 9, 2023, 4:10 a.m. Published Mar 9, 2023, 6:09 p.m.
HUT 8 mining plant (hut8.io)
HUT 8 mining plant (hut8.io)

Operational issues across its bitcoin mining sites are weighing on Hut 8 Mining (HUT) as it tries to complete what would be one of the largest deals in the sector – the company's merger with U.S. Bitcoin Corp.

In mid-November 2022, Hut 8 stopped mining with 7,000 rigs at a site in North Bay, Ontario, due to an ongoing dispute with its energy provider, Validus Power. Hut 8 has now removed all machines from the facility to a site in Medicine Hat, Alberta. Pressed about progress by analysts on the company's earnings call Thursday morning, Hut 8 CEO Jaime Leverton said the firm is assessing opportunities to energize the miners, but didn't give any concrete alternatives.

STORY CONTINUES BELOW
Don't miss another story.Subscribe to the Crypto Daybook Americas Newsletter today. See all newsletters

At its Drumheller site in Alberta, Hut 8 has been facing "electrical issues" that have hit operations. "We are in the early stages exploring supplementary options to mitigate the challenges and hope we have more definitive plan," said the firm's newly appointed chief financial officer, Shenif Visram, during the conference call.

Hut 8 shares are down 8% on Thursday, as are those of its mining peers, as bitcoin slides to its lowest level in a month at $21,450.

Hut 8 did receive a letter of no action from the Canadian competition authority for its proposed merger with U.S. Bitcoin Corp., meaning the authority doesn't plan to challenge the move, Leverton said on the call. The company's main focus is on completing the merger, she said, which will give it access to additional power for mining rigs.

Looking at Q4 results, mining profit plunged to CAD$3.33 million (US$2.4 million) from $39.2 million (US$28.4 million) during the same period a year earlier. For all of 2022, the company mined 3,568 bitcoin, up 28.1% from 2021. Hut 8 reported a net loss of CAD$242.8 million for 2022 compared to a loss of CAD$72.7 million for 2021.

The company earlier this week disclosed sales of bitcoin for the first time in 2021 as it looked to help fund both operating costs and its merger with U.S. Bitcoin Corp.

Read more: Shares of Bitcoin Miner Hut 8 Slump on Merger With US Bitcoin Corp.

CORRECTION (March 9, 18:40 UTC): Clarifies that Hut 8 and Validus were in a dispute, not litigation, in November.

Plus pour vous

Plus pour vous

Recapping Consensus Hong Kong

Consensus Hong Kong 2026 exhibition floor packed with visitors.

Crypto's role in payments for AI, regulatory changes and the digital asset market dominated conversations on the ground.

Ce qu'il:

  • Speakers at CoinDesk's Consensus Hong Kong conference said crypto and stablecoins are likely to become the default payment tools for autonomous AI agents in an emerging "machine economy."
  • Market participants warned that bitcoin, which has already dropped nearly $30,000 in a month, may fall further, with $50,000 seen as the level to watch.
  • Hong Kong regulators are pressing ahead with crypto rules even as others wait to see how U.S. legislation develops.